【Project Overview】This project, undertaken by Shanghai Darun Port Construct-ion Group Co., Ltd., mainly covers construction of 1 trestle of 95.8m×8m, a bridge abutment pier of 8.5m×4.2m, 1 steel approach bridge of 25m×6m, 3 steel crossing bridges of 20.64m×1.0m, 1 steel crossing bridge of 9.54m×1.0m, 5 support pi-ers, 4 supports, 6 steel struts, extension of the stone breakwater by 44m, dismantle of 1 existing support pier and supp-orting works. This project took 140 calendar days with a co-st of RMB 6,698,551.
|