【Project Overview】 This project undertaken by Shanghai Darun Port Constructio-n Group Co., Ltd. mainly covers the water engineering structu-re and the bridge protection piers at the wait berth about 700m away from the Yaogongbu Bridge at the downstream. It is 170m long, 35m at least away from the dredging width line at the bottom. Mooring Dolphins are used for anchorage. 4 protectio-n piers are designed for each bridge (3 bridges preserved te-mporarily: Yuantan Bridge, Wanpu Bridge, Yaogongbu Bridge) along the axis of the waterway. The construction officially start-ed in May, 2010, completed on Jan 10, 2011 and passed the f-inal acceptance on Mar 22, 2011.
|